This letter does not relieve you of your obligations for defect liability and other outstanding obligations under the Contract.
2
摘要:缺陷责任期由起始时间和持续时间决定,其长度由合同双方约定,最长不超过24个月。
Abstract: the defects liability period has a start and duration, of which the length depends on the convention of the contracting parties and is no more than 24 months.
3
在发出缺陷责任证书时,承包商应将根据合同提供的全部图纸、规范和其它文件退还给工程师。
Upon issue of the Defects Liability Certificate, the Contractor shall return to the Engineer all Drawings, Specification and other documents provided under the Contract.